Construction works started in the second half of November 2012 and were following a very tight schedule that led to finish the construction phase by June 2014 with the district heating plant.put in operation.
The test for the proper and flawless operation of the district heating was carried out in October 2014 which provided the contractor to fine tune and fix any operation-related issues prior to the system goes online.